Milestones
Timeline of contractual milestones and their verification state.
Complete
3
At risk
1
Pending
2
Next due
9 Oct
Substructure complete
Complete15 May 2026R 1.3mVerified
Ground floor slab
Complete30 Jun 2026R 840kVerified
Structure to Level 2
Complete21 Aug 2026R 1.1mVerified
Structure to Level 4
At risk9 Oct 2026R 1.2m
Roof deck poured
Pending6 Nov 2026R 620k
Façade watertight
Pending4 Dec 2026R 980k