Daily logs
Field-submitted site logs. Review submitted logs, return for correction, or approve into the project record.
| Date | Status | Sync | Actions |
|---|---|---|---|
| 22 Sep 2026 | Draft | ||
| 21 Sep 2026 | Submitted | ||
| 19 Sep 2026 | Under review | ||
| 18 Sep 2026 | Returned | ||
| 17 Sep 2026 | Approved | ||
| 16 Sep 2026 | Approved | ||
| 15 Sep 2026 | Approved |
22 Sep 2026
T. Moyo · Windy, 19°C
Level 3 column pours (grid C–F). Rebar inspection booked for L4.
21 Sep 2026
T. Moyo · Clear, 22°C
L3 slab formwork 80% complete. Crane downtime 1.5 h (wind).
19 Sep 2026
T. Moyo · Partly cloudy, 20°C
Core wall lift 7 poured. Façade east brackets installed grid 1–4.
18 Sep 2026
L. Petersen · Rain, 15°C
Rain delay until 11:00. Basement waterproofing snag list closed.
17 Sep 2026
T. Moyo · Clear, 24°C
L2 slab stripped. Steel delivery for L4 received and tagged.
16 Sep 2026
T. Moyo · Overcast, 18°C
Concrete cube tests passed (28-day). Lift shaft survey complete.
15 Sep 2026
T. Moyo · Clear, 23°C
L3 column starter bars fixed. Toolbox talk: working at height.