Costs

Cost-code view of approved budget against actual, committed and forecast. Values in ZAR, excluding VAT.

Approved budget

R 8.4m

Actual cost to date

R 5.1m

61%

Expected / committed

R 1.4m

Forecast cost to complete

R 2.2m

Forecast final cost

R 8.6m

Variance

R 218kunfavourable

2.6%

Cost codes

10 of 10

Cost codes
Cost codeApproved budgetActual to dateVariance

01 · Preliminaries & general

R 720 000R 512 000
−R 14kfavourable

02 · Earthworks

R 640 000R 655 000
R 15kunfavourable

03 · Concrete

R 2 450 000R 1 690 000
−R 20kfavourable

04 · Masonry

R 380 000R 96 000
−R 6kfavourable

05 · Steel

R 1 620 000R 1 140 000
Over budgetR 110kunfavourable

07 · Waterproofing & insulation

R 290 000R 244 000
−R 6kfavourable

08 · Doors & windows

R 520 000R 42 000
−R 6kfavourable

09 · Finishes

R 1 180 000R 118 000
−R 16kfavourable

15 · Mechanical

R 340 000R 190 000
−R 4kfavourable

16 · Electrical

R 260 000R 413 000
Over budgetR 165kunfavourable
TotalR 8 400 000R 5 100 000R 218kunfavourable