Stellenbosch Day Clinic

StellenboschPM R. AdamsForeman J. MahlanguOn track

Open in field mode
Stellenbosch Day Clinic — structure under construction
Level 3 · Structure 14 photos today

Level 3 — column pours grid C–F

Tue 22 Sep · 14:05 · Windy, 19°C

LPAVMB

82%

overall completion

Today's log

Draft · offline

Daily logs

Progress by work area

Actual completion (dark) vs planned (light). Orange band = current focus.

  • BB2: 100%, planned 100%
  • BB1: 100%, planned 100%
  • Ground floor slab: 96%, planned 100%
  • L1: 88%, planned 92%
  • L2: 74%, planned 84%
  • L3: 52%, planned 70%
  • L4: 31%, planned 48%
  • Roof deck: 8%, planned 20%
  • Core & lifts: 44%, planned 50%
  • Façade east: 22%, planned 30%
  • Façade west: 12%, planned 25%
  • Finishes L1: 6%, planned 10%
BB2BB1Ground floor slabL1L2L3L4Roof deckCore & liftsFaçade eastFaçade westFinishes L1
Levels 2–4 · Structure phase

Milestones

Next 90 days

Structure to Level 2

Complete

21 Aug 2026R 1.1mVerified

Structure to Level 4

At risk

9 Oct 2026R 1.2m

Roof deck poured

Pending

6 Nov 2026R 620k

Façade watertight

Pending

4 Dec 2026R 980k