Tuesday 22 September · 4 active projects · 2 daily logs awaiting your review.

KH-P2 · Cape Town, Foreshore
Komatsu House — Phase 2
63%
complete · target 68%
Portfolio spend by month
Actual (dark) against planned (light), R thousands
- Feb: R 340k, planned R 380k
- Mar: R 590k, planned R 620k
- Apr: R 810k, planned R 760k
- May: R 860k, planned R 880k
- Jun: R 990k, planned R 920k
- Jul: R 910k, planned R 940k
- Aug: R 920k, planned R 880k
- Sep: R 680k, planned R 860k
- Oct: R 0k, planned R 780k
- Nov: R 0k, planned R 640k
- Dec: R 0k, planned R 420k
Approved budget
R 32.1m
Actual to date
R 19.6m
Forecast final
R 33.7m
Committed
R 6.0m
Recent field activity
T. Moyo saved daily log 22 Sep locally (offline)
12 min ago
A. van Wyk closed scaffold inspection L2 west
48 min ago
B. Sithole submitted daily log 21 Sep
1 h ago
L. Petersen attached 14 photos to L3 column pour
2 h ago
S. Dlamini submitted CO-016 for review
3 h ago
Active projects
Komatsu House — Phase 2
Cape Town, Foreshore · PM N. Jacobs
Salt River Logistics Hub
Salt River, Cape Town · PM N. Jacobs
Stellenbosch Day Clinic
Stellenbosch · PM R. Adams
Paarl Water Works Upgrade
Paarl · PM R. Adams
Daily logs awaiting review
Submitted by field teams
21 Sep 2026 · T. Moyo
36 crew · 284 h · Clear
19 Sep 2026 · T. Moyo
33 crew · 262 h · Partly cloudy
Milestones
Komatsu House — Phase 2
Structure to Level 2
Complete21 Aug 2026R 1.1mVerified
Structure to Level 4
At risk9 Oct 2026R 1.2m
Roof deck poured
Pending6 Nov 2026R 620k
Façade watertight
Pending4 Dec 2026R 980k
Change orders
CO-014 · Additional piling grid F–G
R 186k
CO-015 · Upgrade to fibre-reinforced slab L3
R 93k
CO-016 · Client-requested façade colour change
R 41k
CO-017 · Temporary power relocation
R 19k
Compliance requiring action
Crane operator certificate — J. Ntuli
Certification · due 26 Sep 2026
Scaffold inspection L3 east
Inspection · due 23 Sep 2026
Concrete cube test batch 41
Test result · due 24 Sep 2026
Monthly safety file audit
Audit · due 30 Sep 2026
Material burn rate
Used vs plan to date