Salt River Logistics Hub
Salt River, Cape TownPM N. JacobsForeman B. SitholeAt risk

Level 3 · Structure 14 photos today
Level 3 — column pours grid C–F
Tue 22 Sep · 14:05 · Windy, 19°C
NJSDKN
41%
overall completion
68%
planned
-27 ptsunfavourable
Today's log
Draft · offline
Progress by work area
Actual completion (dark) vs planned (light). Orange band = current focus.
- BB2: 100%, planned 100%
- BB1: 100%, planned 100%
- Ground floor slab: 96%, planned 100%
- L1: 88%, planned 92%
- L2: 74%, planned 84%
- L3: 52%, planned 70%
- L4: 31%, planned 48%
- Roof deck: 8%, planned 20%
- Core & lifts: 44%, planned 50%
- Façade east: 22%, planned 30%
- Façade west: 12%, planned 25%
- Finishes L1: 6%, planned 10%
BB2BB1Ground floor slabL1L2L3L4Roof deckCore & liftsFaçade eastFaçade westFinishes L1
Levels 2–4 · Structure phase
Milestones
Next 90 days
Structure to Level 2
Complete21 Aug 2026R 1.1mVerified
Structure to Level 4
At risk9 Oct 2026R 1.2m
Roof deck poured
Pending6 Nov 2026R 620k
Façade watertight
Pending4 Dec 2026R 980k