22 Sep 2026

T. Moyo · Windy, 19°C

Draft

Level 3 column pours (grid C–F). Rebar inspection booked for L4.

34 crew268 h

21 Sep 2026

T. Moyo · Clear, 22°C

Submitted

L3 slab formwork 80% complete. Crane downtime 1.5 h (wind).

36 crew284 h

19 Sep 2026

T. Moyo · Partly cloudy, 20°C

Under review

Core wall lift 7 poured. Façade east brackets installed grid 1–4.

33 crew262 h

18 Sep 2026

L. Petersen · Rain, 15°C

Returned

Rain delay until 11:00. Basement waterproofing snag list closed.

21 crew146 h

17 Sep 2026

T. Moyo · Clear, 24°C

Approved

L2 slab stripped. Steel delivery for L4 received and tagged.

35 crew276 h

16 Sep 2026

T. Moyo · Overcast, 18°C

Approved

Concrete cube tests passed (28-day). Lift shaft survey complete.

34 crew270 h

15 Sep 2026

T. Moyo · Clear, 23°C

Approved

L3 column starter bars fixed. Toolbox talk: working at height.

32 crew254 h