Reports
Work-area progress, labour productivity and scheduled report packs.
Work areas
12
Behind plan
5
Reports this month
3
Next pack
30 Sep
Progress by work area
- Basement B2 · Substructure100% / 100%
- Basement B1 · Substructure100% / 100%
- Ground floor slab · Structure96% / 100%
- Level 1 · Structure88% / 92%
- Level 2 · Structure74% / 84%
- Level 3 · Structure52% / 70%
- Level 4 · Structure31% / 48%
- Roof deck · Structure8% / 20%
- Core & lifts · Services44% / 50%
- Façade east · Envelope22% / 30%
- Façade west · Envelope12% / 25%
- Finishes L1 · Finishes6% / 10%