Billing

Progress claim PC-08 · billing period 1–30 September 2026. Verified milestones flow into the draft invoice.

Current billing period

Sep 2026

closes 30 Sep

Verified milestones

3 of 6

R 3.2m

Draft invoice total (net)

R 1 297 700

retention R 68k

Invoice status

Draft

PC-08

Invoice line items

Untick a line to hold it for the next claim

Invoice line items
IncludeLine itemThis period
Structure to Level 2 — verifiedR 1 120 000
Ground floor slab — balanceR 60 000
Approved change order CO-014R 186 000
Materials on site — Y16 rebarR 84 000
Net claim this periodR 1 366 000

Milestone verification

Only verified milestones can be billed

Milestones
MilestoneValueStatus
Substructure completeR 1 260 000Approved
Ground floor slabR 840 000Approved
Structure to Level 2R 1 120 000Approved
Structure to Level 4R 1 180 000At risk
Roof deck pouredR 620 000Pending
Façade watertightR 980 000Pending