Reports

Work-area progress, labour productivity and scheduled report packs.

Work areas

12

Behind plan

5

Reports this month

3

Next pack

30 Sep

Progress by work area

  • Basement B2 · Substructure100% / 100%
  • Basement B1 · Substructure100% / 100%
  • Ground floor slab · Structure96% / 100%
  • Level 1 · Structure88% / 92%
  • Level 2 · Structure74% / 84%
  • Level 3 · Structure52% / 70%
  • Level 4 · Structure31% / 48%
  • Roof deck · Structure8% / 20%
  • Core & lifts · Services44% / 50%
  • Façade east · Envelope22% / 30%
  • Façade west · Envelope12% / 25%
  • Finishes L1 · Finishes6% / 10%