Billing
Progress claim PC-08 · billing period 1–30 September 2026. Verified milestones flow into the draft invoice.
Current billing period
Sep 2026
closes 30 SepVerified milestones
3 of 6
R 3.2mDraft invoice total (net)
R 1 297 700
retention R 68kInvoice status
Draft
PC-08Invoice line items
Untick a line to hold it for the next claim
| Include | Line item | This period | |
|---|---|---|---|
| Structure to Level 2 — verified | R 1 120 000 | ||
| Ground floor slab — balance | R 60 000 | ||
| Approved change order CO-014 | R 186 000 | ||
| Materials on site — Y16 rebar | R 84 000 | ||
| Net claim this period | R 1 366 000 |
Milestone verification
Only verified milestones can be billed
| Milestone | Value | Status |
|---|---|---|
| Substructure complete | R 1 260 000 | Approved |
| Ground floor slab | R 840 000 | Approved |
| Structure to Level 2 | R 1 120 000 | Approved |
| Structure to Level 4 | R 1 180 000 | At risk |
| Roof deck poured | R 620 000 | Pending |
| Façade watertight | R 980 000 | Pending |