Milestones

Timeline of contractual milestones and their verification state.

Complete

3

At risk

1

Pending

2

Next due

9 Oct

Substructure complete

Complete

15 May 2026R 1.3mVerified

Ground floor slab

Complete

30 Jun 2026R 840kVerified

Structure to Level 2

Complete

21 Aug 2026R 1.1mVerified

Structure to Level 4

At risk

9 Oct 2026R 1.2m

Roof deck poured

Pending

6 Nov 2026R 620k

Façade watertight

Pending

4 Dec 2026R 980k